13.11.2   Phased site plan                                    applicant may request a minor amendment to
The applicant has three years to start site work or           an approved site plan by submitting a written
building construction undertaken in accordance                statement of the proposed amendments and
with the approved phased site plan and seven years            proposed amended plans to the Planning
to complete the project. Approved amendments                  Authority.
shall have no effect on the expiration date, which is     B. Minor amendments:
based upon the original date of approval. A phased            1.    Are generally consistent with the approved
site plan may be extended by the Planning Authority                 plan.
up to two years from date of expiration. Extension            2.    Do not substantially impact the layout of
requests must be made in writing by the applicant                   buildings and open space.
prior to the expiration of the approval.                      3.    Do not significantly alter the program of
                                                                    proposed uses.
13.11.3 In case of appeal                                     4.    Do not substantially change access,
Where a site plan approval or any related land use                  circulation, or infrastructure on or
approval granted to the same applicant by any                       adjacent to the site.
agency of the City with respect to the same                   5.    Do not otherwise meet thresholds for site
development is appealed to any court by an                          plan review as described in Table 13-A.
opponent of the development, the applicant shall be           6.    Do not affect any condition or
granted extensions, beyond the expiration of said                   requirement of the Planning Board.
approval, where the applicant has exercised due
diligence with respect to defending such appeal.          13.12.3 Major amendments
Extensions shall not last beyond one year from            An applicant may request approval by the review
entry of final judgment.                                  authority of a major amendment to an approved
                                                          site plan by submitting an application for the
13.12 AMENDMENTS TO APPROVED PLANS                        amendment to the Planning Authority. Major
13.12.1 Field changes                                     amendments include changes that exceed the
Changes associated with unforeseen difficulties that      limited criteria for a minor amendment under
arise during the course of construction and               Subsection 13.12.2.
involving such technical detail as utility location and
substitution of equivalent plantings shall be             13.13 CONSISTENCY WITH APPROVED SITE
approved by the Public Works Authority and/or the                  PLANS
Planning Authority. Field changes shall not involve       13.13.1 Sites to be developed and maintained as
substantial alteration of the approved plan or            depicted
conditions imposed by the review authority.               A. Sites shall be developed and maintained as
                                                              depicted in the approved final site plan and the
13.12.2 Minor amendments                                      written submission of the applicant. Any
A. The Planning Authority is authorized to                    deviations from an approved site plan,
     approve minor amendments to site plans. An               including, but not limited to, changes in CITY OF PORTLAND LAND USE CODE | 13-21 SITE PLAN