in Subsection 11.4.3(A), to address the removal       4.   Revegetation activities must meet the
of non- native invasive species of vegetation, or          following requirements for trees and
as a mechanism to allow for development that               saplings:
may otherwise not be permissible due to the                a.   All trees and saplings removed must
vegetation standards, including removal of                      be replaced with native noninvasive
vegetation in conjunction with a shoreline                      species;
stabilization project, the revegetation must               b.   Replacement vegetation must at a
comply with the following requirements.                         minimum consist of saplings;
1.   The property owner must submit a                      c.   If more than three trees or saplings
     revegetation plan, prepared with and                       are planted, then at least three
     signed by a qualified professional, that                   different species shall be used;
     describes revegetation activities and                 d.   No one species shall make up 50% or
     maintenance. The plan must include a                       more of the number of trees and
     scaled site plan, depicting where                          saplings planted;
     vegetation was, or is to be removed, where            e.   If revegetation is required for a
     existing vegetation is to remain, and where                shoreline stabilization project, and it is
     vegetation is to be planted, including a list              not possible to plant trees and
     of all vegetation to be planted.                           saplings in the same area where trees
2.   Revegetation must occur along the same                     or saplings were removed, then trees
     segment of shoreline and in the same area                  or sapling must be planted in a
     where vegetation was removed and at a                      location that effectively reestablishes
     density comparable to the pre-existing                     the screening between the shoreline
     vegetation, except where a shoreline                       and structures; and
     stabilization activity does not allow                 f.   A survival rate of at least 80% of
     revegetation to occur in the same area and                 planted trees or saplings is required
     at a density comparable to the pre-existing                for a minimum five year period.
     vegetation, in which case revegetation           5.   Revegetation activities must meet the
     must occur along the same segment of                  following requirements for woody
     shoreline and as close as possible to the             vegetation and other vegetation under
     area where vegetation was removed:                    three feet in height:
3.   If part of a permitted activity, revegetation         a.   All woody vegetation and vegetation
     shall occur before the expiration of the                   under three feet in height must be
     permit. If the activity or revegetation is not             replaced with native noninvasive
     completed before the expiration of the                     species of woody vegetation and
     permit, a new revegetation plan shall be                   vegetation under three feet in height
     submitted with any renewal or new permit                   as applicable;
     application.                                          b.   Woody vegetation and vegetation
                                                                under three feet in height shall be CITY OF PORTLAND LAND USE CODE | 11-9 SHORELAND OVERLAY ZONE