and no structure in such an area which is               12.7 VARIANCES AND APPEALS
     developed or substantially improved shall be            12.7.1 Authority
     occupied until a certificate of compliance is           A. The Zoning Board of Appeals of the City of
     issued by the Building Authority. Said certificate          Portland may, upon written application of an
     of compliance shall be issued only after the                aggrieved party, hear and decide appeals where
     Building Authority has received all permits and             it is alleged that there is an error in any order,
     certificates from the applicant as required by              requirement, decision, or determination made,
     this article.                                               or failure to act, in the administration or
C. For new construction or substantial                           enforcement of the provisions of this article.
     improvement of any elevated structure, the              B. The Board of Appeals may authorize variances,
     applicant shall submit to the Building Authority:           meaning the granting of relief from the
     1.   An elevation certificate (FEMA form FF-                provisions of this article, as authorized in
          206-FY-22-152) completed by a                          Subsection 2.3.11 except:
          professional land surveyor for compliance              1.   As otherwise expressly provided in
          with Subsection 12.4.5(H), (I), (J), or (R).                Subsection 2.3.11(E).
     2.   For structures in Zones VE and Coastal AE,             2.   Variances shall not be granted within any
          a written certification by a registered                     designated regulatory floodway if any
          professional engineer or architect shall be                 increase in flood levels during the base
          provided to the Building Authority stating                  flood discharge would result.
          that the design and methods of
          construction used are in compliance with           12.7.2 Standards
          the applicable provisions of Subsection            Subsection 2.3.11 notwithstanding, variances from
          12.4.5(R)(2)(b), (c), and (d).                     the requirements of this article shall be granted only
D. The applicant shall submit written notification           upon:
     to the Building Authority that the development          A. A showing of good and sufficient cause.
     is complete and complies with the provisions of         B. A determination that should a flood
     this article.                                               comparable to the base flood occur, the
E.   Within 10 working days, the Building Authority              granting of a variance will not result in
     shall review the elevation certificate (FEMA                increased flood heights, additional threats to
     form FF-206-FY-22-152) and the applicant’s                  public safety, or public expense, or create
     written notification and, upon determination                nuisances, cause fraud or victimization of the
     that the development conforms with the                      public, or conflict with existing local laws or
     provisions of this article, shall issue a certificate       ordinances.
     of compliance.                                          C. A showing that the issuance of the variance will
                                                                 not conflict with other state, federal, or local
                                                                 laws or ordinances. 12-18 | CITY OF PORTLAND LAND USE CODE FLOODPLAIN MANAGEMENT