Keeney v. Hereford Concrete Products, Inc., 911 S.W.2d 622 (1995)

Citation
Keeney v. Hereford Concrete Products, Inc., 911 S.W.2d 622 (1995)
Parent Document
Keeney v. Hereford Concrete Products, Inc., 911 S.W.2d 622 (1995)
Jurisdiction
Missouri (state)
Effective Date
1995-12-19

Other Sections in This Document (72)

Full Text

415 chars
[A]t the time of the alleged retaliatory action, no employer-employee relationship existed between [Keeney] and Hereford Concrete Products, Inc., because no contracts for the payment of money existed between [Keeney] and Hereford Concrete Products, Inc., as pled, and because the evidence does not demonstrate that the alleged retaliatory action had any impact *624on [Keeney’s] future employment or em-ployability.