United Housing Foundation, Inc. v. Forman, 421 U.S. 837 (1975)
Effective Date
1975-10-06

Other Sections in This Document (195)

Full Text

700 chars
Respondents maintained that the following material facts were omitted: (i) the original estimated cost had never been adhered to in any of the previous Mitchell-Lama projects sponsored by UHF and built by CSI; (ii) petitioners knew that the initial estimate would not be followed in the present project; (iii) CSI was a wholly owned subsidiary of UHF; (iv) CSI’s net worth was so small that it could not have been legally held to complete the contract within the original estimated costs; (v) the State Housing Commissioner *845had waived his own rule regarding liquidity requirements in approving CSI as the contractor; and (vi) there was an additional undisclosed contract between CSI and Riverbay.