Boston Code of Ordinances § 7-2.2

Citation
Boston Code of Ordinances § 7-2.2 (c)
Parent Document
Boston Code of Ordinances § 7-2.2
Jurisdiction
Boston (municipal)

Other Sections in This Document (288)

Full Text

1,001 chars
(c)   Power Purchase Agreements. Buildings may mitigate CO2e emissions from electricity use by entering Power Purchase Agreements for energy generated by renewable non-emitting fuel sources; provided that:
            1.   The energy purchased pursuant to a Power Purchase Agreement is generated during the compliance period for which a building is mitigating CO2e emissions;
            2.   The Renewable Energy Certificates associated with the energy purchased under a Power Purchase Agreement are retired by the building owner within six months after the end of the compliance period in which used; and
            3.   The Power Purchase Agreement complies with any additional or different requirements set forth in the regulations, as may be amended from time to time, including, but not limited to, additionality criteria. In the event of a conflict between the requirements for Power Purchase Agreements in this provision and the regulations, the requirements in the regulations shall prevail.