Batson v. Clark, 980 S.W.2d 566 (1998)

Citation
Batson v. Clark, 980 S.W.2d 566 (1998)
Parent Document
Batson v. Clark, 980 S.W.2d 566 (1998)
Jurisdiction
Kentucky (state)
Effective Date
1998-10-16

Other Sections in This Document (163)

Full Text

526 chars
The construction of the pole barn consisted of ten poles, metal sheets, trusses and a roof. The poles were placed two feet in the ground into one square foot of poured concrete. The pole bairn had no footer, no flooring and no foundation. The existing building’s gas and electrical supply had to be tapped into in order to supply such to the pole barn. A breezeway was built from the existing building to the pole barn. The breezeway was connected to the pole barn and the existing building with two by fours and metal screws.