SUNPIN ENERGY SERVICES, LLC, & Another v. ZONING BOARD OF APPEALS OF PETERSHAM (2025)

Citation
SUNPIN ENERGY SERVICES, LLC, & Another v. ZONING BOARD OF APPEALS OF PETERSHAM (2025)
Parent Document
SUNPIN ENERGY SERVICES, LLC, & Another v. ZONING BOARD OF APPEALS OF PETERSHAM (2025)
Jurisdiction
Massachusetts (state)
Effective Date
2025-07-09

Other Sections in This Document (43)

Full Text

561 chars
Background.  The following facts are undisputed.[4]  The entire town is zoned residential-agricultural.  The town has established a solar electric overlay district (SEOD) that allows for "large-scale ground-mounted solar electric installation[s] (greater than 10 kW [kilowatts])" as of right.  However, any such installations located outside the SEOD require a special permit in accordance with §§ 11.2 and 18 of the bylaw.[5]  The proposed site of the project is on property located outside of the SEOD, thereby requiring a special permit and site plan review.