York v. Steward, 21 Mont. 515 (1898)

Citation
York v. Steward, 21 Mont. 515 (1898) 1.
Parent Document
York v. Steward, 21 Mont. 515 (1898)
Jurisdiction
Montana (state)
Effective Date
1898-11-07

Full Text

2,677 chars
1. Much difficulty has been experienced in the effort to determine the exact ground upon which the defendants, in their first defense and counterclaim, intend to rely. The.matters *517there stated as constituting both a defense and a counterclaim are set forth in a manner so obscure, and with such disregard of the rule requiring conciseness and clearness, that a demurrer attacking the part of the answer now being considered, for want of certainty, as well as for ambiguity, would have been well interposed. Since, however, no objection was taken in the court below or here to the answer upon any ground whatsoever, we have examined the first defense and counterclaim as pleaded, and, after some hesitation, arrive at the conclusion that the pleader intended to aver, substantially, that, on, or just before, the execution of the lease, and while the defendants were negotiating with plaintiff therefor, plaintiff warranted that the building was in all respects suitable for the purpose of carrying on therein the piano and musical instrument business, in which defendants werl engaged; that the basement would be ceiled, and put in good condition, and a new sidewalk laid; that defendants, relying upon these representations and warranties, entered into the lease, and in pursuance of the lease went into possession of the building, and placed their stock of musical instruments therein, and remained in possession until August 31, 1893; that the building was defectively constructed; that it was unfit for defendants’ business, and that by reason of the defective construction of the plumbing and water fittings in the second story, which was occupied by and in the possession of plaintiff, the sinks and closets situated in the second story, and under the control of plaintiff, were allowed to overflow, and the water permitted to run down into the defendants’ place of business, and upon defendants’ merchandise, whereby the stock of goods was injured; that defendants repeatedly notified plaintiff of the defective condition of - the plumbing and fittings in the building, but that plaintiff refused and neglected to remedy such defects, by which default plaintiff permitted a continuing nuisance to exist; that, because of the defective construction of the building, it was unfit for the use for which it was rented by the defendants, and was untenantable; and that by reason of the representations and warranties of the plaintiff as to the *518condition of the building, and by reason of its unfitness for the purpose for which it was warranted by plaintiff, and by reason of the injury done by the water, defendants were damaged in their business in the sum of §250.