Skip to main content
DRAFT FOR ATTORNEY REVIEW — NOT FINAL

Samuelson v. A.A. Quality Construction, Inc., 230 Mont. 220 (1988)

Citation
Samuelson v. A.A. Quality Construction, Inc., 230 Mont. 220 (1988)
Parent Document
Samuelson v. A.A. Quality Construction, Inc., 230 Mont. 220 (1988)
Jurisdiction
Montana (state)
Effective Date
1988-01-21

Other Sections in This Document (25)

Full Text

456 chars
During construction, the Samuelsons noted that the basement area *222accumulated water several times. Mr. Aldinger initially explained that the water entered the structure through window cutouts that were not yet covered with glass. Later the parties realized that the basement had a water seepage problem. A.A. Quality attempted to correct the, problem by installing an exterior cement slab to divert water and by repairing rock pockets in the foundation.